While reviewing prototypes, the quality team found some deviations that do not affect the main functionality but have the potential to be an issue in the future. To avoid major problems in the future, the team recommends corrective actions that will require additional funds. The project is already struggling to stay on budget and has even used some of the contingency reserves.
What should the project manager do?

الخيارات

  • A Evaluate and initiate the change request process with the stakeholders.
  • B Ask the product designer why the deviation was not considered in the design phase.
  • C Ask the quality team to discard the sample and test again with a new sample.
  • D Report to the project sponsor that the product is working and the project is struggling with the budget.