اختبار شهادة إدارة المشاريع Project Management Professional (PMP)

السؤال 198 من 874

كل الأسئلة

A project manager joins a team that is providing a customized enterprise resource planning (ERP) system to a client. A potential design problem is identified by the development team. After reviewing this issue with the project owner and team members, all agreed to revise the design to avoid a system defect when deployed. The design is already approved.
What should be the project manager's next steps?

الخيارات

  • A Make a change request and get formal approval from the project owner.
  • B Inform the client of the problem and follow the change request process.
  • C Conduct a proof of concept to make sure there are no problems in the revised design.
  • D Amend the design specifications and pass them to the development team for reprogramming.

النقاشات