اختبار شهادة إدارة المشاريع Project Management Professional (PMP)

السؤال 196 من 874

كل الأسئلة

A project team is experiencing delays in completing a task that turned out to be more complex than initially estimated. This is a critical task that could impact current iteration goals.
What two actions will help the team initially address this obstacle? (Choose 2)

الخيارات

  • A Create a risk management plan.
  • B Review and update dependencies.
  • C Escalate the issue to the project sponsor.
  • D Schedule a retrospective.
  • E Conduct a root cause analysis.