Due to delays on some activities, one of the project team members has increased the scope without any approval. What should the project manager do next?

الخيارات

  • A Update project documentation with the new scope.
  • B Add team members to the project to avoid more schedule delays.
  • C Remove the changes to match the original requirements.
  • D Evaluate the impacts of the changes that were made to the project.