A vendor supplying a piece of specialized equipment for a project has reported the potential for a delivery delay due to a technical issue with the sub-supplier. To stay on schedule, the vendor proposed replacing the sub-supplier's component with a similar part that is different from the one that is stipulated in the project specifications.
What should the project manager do next?

الخيارات

  • A Consult with a subject matter expert (SME) to see if the proposed change is acceptable.
  • B Insist on using the component per the project specifications and air freight the equipment to mitigate the delay.
  • C Instruct the vendor to use the part that is compliant with the project specifications and update the schedule.
  • D Accept the proposed replacement in order to keep procurement activities on track.