The project team is planning a schedule with limited information. The team is having issues identifying the detailed tasks and estimating task duration.
Which three techniques should the project manager use? (Choose 3)

الخيارات

  • A Iterations and reviews to continuously keep adapting the plan
  • B Bottom-up estimating based on a work breakdown structure (WBS)
  • C Rolling wave planning and an adaptive approach
  • D Relative estimation to determine the task or deliverable sizes
  • E Gantt chart that includes milestones and deadlines