A project interfaces with other projects that are in the same portfolio but are being developed in international locations. One of the international projects has suggested a tactical change that needs to be implemented in this project.
What should the project manager do next?

الخيارات

  • A Keep the focus on the priority items while the change goes through the change control process.
  • B Implement the change request as soon as possible to avoid accumulating new scope.
  • C Use the team's connections with international colleagues to get early warnings on future changes.
  • D Reject the change request since it may negatively impact the project's performance.