اختبار شهادة إدارة المشاريع Project Management Professional (PMP)

السؤال 131 من 874

كل الأسئلة

A laboratory is launching a new product, defined to be executed in eight iterations with a fixed release date. At the beginning of the second iteration, the project manager realizes that a significant regulatory feature is missing in the project backlog.
What should the project manager do?

الخيارات

  • A Ask the product owner to add the missing feature in the backlog.
  • B Increase the capacity of the team to include the missed feature.
  • C Invite stakeholders to discuss the impact of adding the regulatory feature.
  • D Estimate the related cost and ask for a project extension.