A project manager is acting as a servant leader and is struggling to make deadlines on a critical roadway construction project that is falling behind schedule due to a low-performing team. In order to get the project back on track, what should the project manager do first?

الخيارات

  • A Contact each team member to inform them that further schedule slips will not be tolerated by the project sponsor.
  • B Notify the project sponsor that the team is underperforming and request additional resources to compress the schedule.
  • C Begin holding daily meetings to assign each team member discrete tasks with specific due dates.
  • D Empower the team members to conduct their job activities and hold each person accountable to improve the schedule.