A construction project for a nuclear power plant will reduce the region’s energy dependence on external electricity supplies. The project manager has received support for the project from several leaders in the region. However, some people from the government want to stop this project to focus on developing renewable energy sources.
Which stakeholders should the project manager include in the stakeholder engagement plan?

الخيارات

  • A Stakeholders who have been identified and who have needs and a potential impact on the project.
  • B Stakeholders who are supporting the project in order to obtain additional resources.
  • C Stakeholders who disagree with the project so as to proactively manage their expectations.
  • D Stakeholders who are selected by the project sponsor who have a potential impact on the project.