A project manager realizes that the team members are new to the hybrid approach and do not value standup meetings. Team members often arrive late, digress into solutioning, or skip the meetings altogether.
How should the project manager improve this situation with the project team?

الخيارات

  • A Include a daily brainstorming session in the standup meetings to resolve pending issues.
  • B Ask the product owner to remove team members who do not comply with standup meeting rules.
  • C Engage the project team in implementing and improving key aspects of the standup meetings.
  • D Send a daily retrospective report to all team members instead of holding standup meetings.