An organization is embarking on the deployment of a new digital solution that will revolutionize purchasing services. The project manager has created all the necessary plans and activities to ensure a successful integration and solution launch. There is a risk of a partner's system being unavailable which could impact the project negatively.
What key activity is needed to ensure the project's success?

الخيارات

  • A Mitigate the risk by developing alternative plans to make the solution ready and available without full integration capabilities.
  • B Continuously monitor the risk of the partner system's unavailability, and put the proper resolution plans in place in case the risk materializes into an actual issue.
  • C Eliminate the risk by mandating the partner to change the system settings to facilitate an easier integration with the new solution.
  • D Communicate to the project stakeholders that full integration may not be possible and that the project will potentially be delayed as a result.