A company has decided to initiate a project to eliminate a sales channel that has been unprofitable for the past 3 years. Some members of the project team are pessimistic about the project.
What should the project manager do in this situation?

الخيارات

  • A Provide team members with specific and clear instructions on the project objectives and tasks.
  • B Communicate the project's impact and plans to engage the project team throughout the project.
  • C Escalate the team's concerns and ask the project sponsor to change the team's composition.
  • D Engage the functional managers to describe the project's impact to the team members directly.