A project manager implementing a hybrid project is dealing with multiple stakeholders in a rapidly changing business environment. How should the project manager ensure that the needs of stakeholders are consistently met?

الخيارات

  • A Assign one team member to one stakeholder to ensure that the responsible team member is conversant with the needs of the stakeholder.
  • B Add more iterative techniques to improve stakeholder learning.
  • C Identify all the critical stakeholders during project initiation.
  • D Use iterative life cycles involving stakeholders to enable the team to improve the product end result through successive prototypes.