A system migration project is in its closing stage. The project manager is being pressured to close the project. The project manager communicated to all stakeholders; however, the last department to migrate indicated that they have not received the notification.
What should the project manager do?

الخيارات

  • A Escalate the issue to the project sponsor and upper management.
  • B Log the issue and assign it to the project team member(s).
  • C Close out the project and tell the manager to open a service desk ticket.
  • D Report the issue during the next status meeting at the end of the week.