A company wants to increase the commercial value of one of its products in a highly competitive market. In order to do this, the company commissions a project to create a prototype. The team constructs the prototype incrementally.
Which action should the project manager take as a priority?

الخيارات

  • A Deliver business value as soon as possible.
  • B Emphasize the use of Kanban methodology.
  • C Implement a plan-do-check-act (PDCA) cycle.
  • D Ensure the project sponsor is aware of the go-to market date.