A project requires the procurement of a large amount of equipment that needs to be on-site before any other activity can begin. The procurement department has a lengthy approval process.
What should the project manager do?

الخيارات

  • A Ask the project sponsor to expedite the vendor selection process.
  • B Work with the procurement team to find alternative options.
  • C Use the existing equipment and replace it later with the new equipment.
  • D Contact the vendor that supplied similar equipment for a previous project.