A project manager has recently joined a small company. The company’s chief operating officer (COO) asked the team to skip some steps in the process in order to work more quickly. The project manager wants to ensure that these steps are not skipped in the future.
What should the project manager do?

الخيارات

  • A Escalate the issue to the other executive leadership members.
  • B Redesign the process so the team can move more quickly.
  • C Schedule a review of the process steps with the team and the COO.
  • D Notify all team members that all steps in the process must be completed.