A project manager is working on multiple building construction projects using a predictive project management approach. Senior leadership within the organization is promoting the inclusion of more agile practices into the current project methodologies. The project sponsor now wants the projects to use more agile methodologies.
Before mandating any agile methods to be used in a project, what should the project manager do first?

الخيارات

  • A Shift all existing projects to agile methodologies with a strict timeline.
  • B Provide agile training to those who will be part of the project team.
  • C Pause the current projects to align them to the new agile cadence.
  • D Assess the organizational culture and readiness for the transformation.