A project manager has taken over a project that has been without a project manager for the last couple of weeks. The team is feeling lost and there are a few team members who are confused about the next steps and the final outcome of the project.
What should the new project manager do?

الخيارات

  • A Escalate the situation to the steering committee and request that more time be allotted to the project.
  • B Ask the project sponsor to provide team members with a project direction regarding outcomes.
  • C Avoid conflict and let the team self-organize on how they want to work on the project tasks.
  • D Set short-term goals in order to create a winning culture internally and praise team members for achieving them.