A team is finishing the third release to present to the stakeholder as part of a demonstration. The company that subcontracts the developers has communicated that there is a cash flow problem and the company will not be able to provide the same resources for the next iterations.
What should the project manager do next?

الخيارات

  • A Escalate the situation to the project sponsor for a possible resolution.
  • B Work with the product owner to prioritize the product backlog.
  • C Analyze the impact against the release plan if the blocker is not addressed.
  • D Create a risk register to track the risks and request additional budget.