A self-organizing team was delivering as committed. The team accepted a development task with new technology and the iterations started to have reduced velocity.
What management decision is suited for this situation?

الخيارات

  • A Move team members who are not performing from the team.
  • B Add new members to the team and increase the velocity.
  • C Provide opportunity for team members to learn and adjust to the technology.
  • D Re-assign the project to a team that has worked with this technology.