During project execution, the project manager notices that the work performance reports have deteriorated drastically in less than two weeks. The project team in country A is complaining about delays resulting from holidays occurring in country B that have impacted their project team.
How should the project manager handle this situation?

الخيارات

  • A Perform conflict management using the project’s resource management plan.
  • B Implement fast-tracking to compress the schedule and improve the SPI.
  • C Implement crashing to compress the schedule and improve the schedule performance index (SPI).
  • D Review the risk management plan to evaluate the probability and impact of these delays.