اختبار شهادة إدارة المشاريع Project Management Professional (PMP)

السؤال 798 من 874

كل الأسئلة

A team is working on a hybrid project. Due to different interpretations of the project requirements, the deliverables are not aligned to the expectations.
What steps should the project manager have taken to prevent this?

الخيارات

  • A Ensure the team receives continuous feedback from customers/users.
  • B Update the project management plan in order to get back on track.
  • C Submit a change request to adjust the project scope.
  • D Ensure the team understands all additional project requirements.