A new project needs to be submitted for urgent funding approval. The project, which will use a new technology, is vital to the organization. The entire Scrum team has worked together for over 3 years on multiple projects and delivered the previous project under the approved budget.
Which estimation technique should the project manager implement in this context?

الخيارات

  • A Definitive estimate
  • B Order of magnitude
  • C Story points
  • D Budget estimate