A global company is executing a strategic project to upgrade a legacy enterprise system. The company uses a hybrid approach to project management and has just completed the first sprint. A team member provided ideas to improve the testing process during the sprint retrospective.
What is the next step for the project manager?

الخيارات

  • A Organize a demonstration of the changes in the enterprise system.
  • B Request that all team members think of ideas to improve processes.
  • C Facilitate a daily standup with the team to track the implementation of changes.
  • D Document the lessons learned and implement improvements in the next sprint.