After a meeting with the customer, the project manager receives special recognition because the project is always on schedule. Later that day, the project manager attends a regular project team meeting to follow up on the status of the deliverables.
What should the project manager do in the project team meeting?

الخيارات

  • A Start planning how to improve the dates of next deliverables.
  • B Follow the meeting agenda and make a list of the next deliverables.
  • C Share the customer feedback with the project team.
  • D Document this feedback in the meeting minutes.