A project requires testing of the final product to be done at another department's testing facility, which is known for having low availability. This situation could potentially impact the project schedule.
What should the project manager do next?

الخيارات

  • A Update the risk register.
  • B Update the lessons learned register.
  • C Update the project schedule.
  • D Update the issue log.

النقاشات

لا توجد نقاشات منشورة لهذا السؤال حالياً.