A project is about to start. The project manager has found that the client does not have an appropriate knowledge management system and does not have a requirement for it.
What should the project manager do?

الخيارات

  • A Ask the team to collect the knowledge locally and share it at the end of the project.
  • B Provide just-in-time knowledge to the client, upon request.
  • C Utilize the cloud wiki to collect the necessary knowledge.
  • D Coordinate with the team and the project stakeholders to collect the knowledge.