A project manager has been assigned to a project that is consolidating regional operations into a global operation. The project sponsor explains that some efficiencies could be obtained from this unification. However, the sponsor is not sure if this effort will have a return on investment (ROI) and would like the project manager's opinion.

What should the project manager do?

الخيارات

  • A Request the project sponsor to include a commitment from the stakeholders to reduce costs within the project scope.
  • B Suggest conducting a detailed cost-benefit analysis for financial feasibility before the start of the project.
  • C Recommend conducting an initial high-level feasibility assessment to estimate the cost and benefits.
  • D Explain that the project manager is limited to demonstrating earned value (EV) from the project execution perspective.
  • E Request the project sponsor to include a commitment from the stakeholders to reduce costs within the project scope.
  • F Suggest conducting a detailed cost-benefit analysis for financial feasibility before the start of the project.
  • G Recommend conducting an initial high-level feasibility assessment to estimate the cost and benefits.
  • H Explain that the project manager is limited to demonstrating earned value (EV) from the project execution perspective.