A project lead was recently elected to complete the execution of a legacy project for a water filtration plant due to the project director's reassignment. The project lead has been on five similar projects in the recent past. The client has challenged the completion status due to a lack of construction evidence. The client has also indicated their intention to apply performance-associated penalties that are detailed in the contract.

What should the project lead do?

الخيارات

  • A Inform the project director of the change and complete the project so as to not incur any penalties.
  • B Accept the client's observations and pay the penalties as per the project contract details.
  • C Request for the recall of the project director to investigate the situation and negotiate potential penalties.
  • D Investigate the client's project reports and proceed to negotiate the levying of any penalties.