A project manager is working on a software development project. Software development will be carried out through a partnership with a vendor based on a list of initial requirements not yet completely defined.

What type of contract and project approach should the project manager consider?

الخيارات

  • A Fixed-price contract with a predictive approach
  • B Memorandum of understanding (MOU) with an agile approach
  • C Time and materials (T&M) with an agile approach
  • D Cost reimbursable contract with a predictive approach