A project manager was notified about a new regulatory requirement that could impact the project schedule. What should the project manager do first?

الخيارات

  • A Consult the project management plan for guidance on addressing the regulatory requirement.
  • B Update the schedule and project risk register according to the regulatory requirement.
  • C Assess the impact of implementing the potential regulatory requirement on the project.
  • D Increase the amount of slack in the critical path to reduce the impact of the regulatory requirement.