An experienced team member has recently started performing at a slower pace and is no longer engaged in various team conversations. What should the project manager do?

الخيارات

  • A Incentivize the team with prizes for increased performance and engagement in order to persuade the team member to resume previous performance.
  • B Meet with human resources (HR) to determine the problem and develop a recommendation based on the results.
  • C Ask the direct manager to reach out and try to identify the problem, then provide that information back to the project manager.
  • D Inform the team member that a change in performance and engagement is noticed and work together to develop a solution for improvement.