The sponsor calls the project manager and questions why the stakeholders have not received updates for over 1 month. The project recently implemented a project management information system (PMIS) that provides real-time access to various project status measurements and information. The project manager is certain that all stakeholders have the opportunity and permissions for status updates.

How should the project manager proceed?

الخيارات

  • A Call and apologize to the team members and provide an update on how this issue was caused.
  • B Request the operations support team to troubleshoot and determine the root cause of the issue.
  • C Review the communications management plan and stakeholder engagement plan for the project.
  • D Obtain a list of the affected stakeholders and email the current status information to them.