A project team strongly encourages the project manager to purchase an application that will significantly reduce work time. Without the application, the deadline might be missed. However, the purchase will impact the project cost. The sponsor would like to explore a less expensive application that will save the team’s time.
What should the project manager do?

الخيارات

  • A Create a decision tree.
  • B Analyze assumptions and constraints.
  • C Purchase the application.
  • D Raise a change request.