A key stakeholder of a project wants to include additional work before completion. What should the project manager do?

الخيارات

  • A Collaborate immediately with the stakeholder to complete the additional work.
  • B Request the additional work through governance.
  • C Prioritize the additional work in the backlog.
  • D Meet with the stakeholder and explain that additional work cannot be added.