اختبار شهادة إدارة المشاريع Project Management Professional (PMP)

السؤال 592 من 874

كل الأسئلة

A project manager assigned to an agile project realizes that after iteration demos new user stories to fix issues reported by the product owner are not included in prioritization of the following sprint. This has led to a high number of unprioritized stories in the backlog and will lead to delay of the product release.
How should the project manager address this situation?

الخيارات

  • A Ask the team and product owner to reprioritize the user stories in the backlog for an updated iteration schedule.
  • B Add additional iterations to the schedule to accommodate for the work required on the stories.
  • C Ask the team to include the user stories as spikes in the next iteration to bring the project back on schedule.
  • D Review the minimum viable product (MVP) user stories and ensure all related stories are prioritized.

النقاشات

لا توجد نقاشات منشورة لهذا السؤال حالياً.