اختبار شهادة إدارة المشاريع Project Management Professional (PMP)

السؤال 590 من 874

كل الأسئلة

A project is delayed considerably from its original completion date for various reasons. The client attributes the delays to the contractor and is going to impose liquidating damages. The project manager of the contracting company reviews the schedule and observes that, though some activities were delayed by the contractor, the critical activity was delayed by the client.
What should the project manager of the contracting company do?

الخيارات

  • A Check the contractual terms about liquidated damages and reject if not applicable.
  • B Schedule a detailed analysis of the delays using cause and effect.
  • C Record that the delay is attributable to the client and request a meeting.
  • D Meet with the sponsor to analyze the delays and the associated liquidated damages.

النقاشات

لا توجد نقاشات منشورة لهذا السؤال حالياً.