A company faces challenges and decides to cut a few product features from the main project due to market conditions. During a status meeting, a new stakeholder expresses concern about the discrepancies between the current deliverables and the deliverables agreed upon in the project charter.
What should the project manager do first?

الخيارات

  • A Determine the root cause of the discrepancy with the project team and agree on the project scope.
  • B Ask the project team to increase the number of updates provided to the stakeholder.
  • C Ask the new stakeholder to submit a change request to the change control board (CCB).
  • D Review the project objectives for alignment with the intended corresponding business value.