اختبار شهادة إدارة المشاريع Project Management Professional (PMP)

السؤال 575 من 874

كل الأسئلة

A large, multinational organization is reevaluating its policy on project management approaches. Team members are complaining about having different processes for each project they are on. Currently, predictive, agile, and hybrid methodologies are being used. A project manager is now part of a team working on standard criteria for approach selection for new projects.
What should the project manager recommend?

الخيارات

  • A Determine the types of projects, constraints, and resources to initiate standard tailoring.
  • B Identify the most commonly used methodology currently and apply that to all future projects.
  • C Simplify the approaches to use either a single agile or a single predictive methodology.
  • D Incorporate both structure and flexibility through custom tailoring for all projects.

النقاشات

لا توجد نقاشات منشورة لهذا السؤال حالياً.