At the beginning of a project, a project manager is asked to provide human resources (HR) with an evaluation of every team member's performance. This evaluation will be delivered at the end of the project.
How should the project manager approach this request?

الخيارات

  • A Ask the project team how they would prefer to be evaluated and use those criteria to share results with HR.
  • B Meet with HR at the end of the project and provide a confidential evaluation of every team member's performance.
  • C Establish a set of objective and measurable performance indicators for evaluating team members and share it with the team.
  • D Evaluate the project team members' performance based on whether the completed project fulfills its intended objectives.