اختبار شهادة إدارة المشاريع Project Management Professional (PMP)

السؤال 567 من 874

كل الأسئلة

Companies A and B are codeveloping a cutting-edge technology product. Based on customer feedback, the marketing department urgently requests a new feature in 2 weeks. Company A’s front end is ready, but company B requires 4 weeks to deliver the complete back end and is busy with the current release.
What should the project manager do to obtain agreement from both companies and acceptance from marketing?

الخيارات

  • A Add the new feature to the list for the next release and continue working on the current release.
  • B Stop the current release work for 4 weeks in order to work and deliver the new feature completely.
  • C Plan the delivery of a minimum viable feature in 2 weeks to enable early showcasing of business value.
  • D Create a special release 4 weeks after the current release to deliver the new feature in its entirety.

النقاشات

لا توجد نقاشات منشورة لهذا السؤال حالياً.