During a project review session with key stakeholders, a senior manager raises a concern that the product being shown is not meeting the client’s expectations. The project manager has noticed that although the team is meeting project deadlines, there are a large number of open quality issues that have not been addressed.
What should the project manager do?

الخيارات

  • A Meet with the project stakeholders to review the scope and ask for a time extension to address the quality issues.
  • B Work with the project team to identify the gaps and address the critical issues based on defined outcomes.
  • C Advise the team to continue moving forward because meeting the milestones is more important and the issues can be fixed later.
  • D Ask the team to reprioritize and focus on fixing the quality issues that were identified by the stakeholders during the meeting.