Two project team members are updating the schedule but cannot reach an agreement on when two milestones are due. Each team member believes they are correct based on the documents they have available.
What should the project manager do first to finalize the schedule?

الخيارات

  • A Ask the two team members to meet to work the discrepancy out and let the project manager know the outcome.
  • B Engage the two team members to investigate the reasons each believes that their documents are correct.
  • C Ask the team members to send the documents and apply expert judgment to update the schedule.
  • D Update the schedule so it is available for team members to continue the work and figure out the discrepancy later.