A project manager is implementing a project similar to a previous one that required strict adherence to occupation, health, and safety (OHS). Both projects are for the same client whose business environment is highly regulated. However, this time the client does not appear to be concerned about OHS requirements.
What should the project manager do first?

الخيارات

  • A Discuss the OHS requirements with the client.
  • B Discuss the OHS requirements with the regulatory organization.
  • C Relax the OHS requirements as the client is not concerned.
  • D Apply the same OHS requirements as the previous project.