A company is working on the prototype of a new contract document that includes visual elements. The product owner shared the project sponsor's feedback about the elements to be included, but the project team pushed back. However, when the project sponsor spoke with the team, they confirmed that all of the changes are possible.
How should the project manager mitigate this situation?

الخيارات

  • A Submit a change request to replace the product owner.
  • B Execute a retrospective meeting to solve the misalignment.
  • C Review the actions listed in the risk management plan.
  • D Review and update the organizational process assets (OPAs).