A project team is concluding the final sprint to deliver two work packages. However, the scrum master has not scheduled sprints for three packages on the critical path, which is going to cause the schedule performance index (SPI) to trend toward 0.90 the following month.
What should the project manager do first?

الخيارات

  • A Ask the scrum master to identify why sprints are in process for work that is not on the critical path.
  • B Instruct the scrum master to suspend the current sprints and initiate the critical sprints immediately.
  • C Evaluate the schedule performance index (SPI) trend for slack to enable all five sprints while maintaining the cost performance index (CPI).
  • D Contact the project sponsor to request adjustment to the completion date and to enable the current workflow.