During user acceptance testing (UAT), a manager declined a core application functionality that was originally requested by a subject matter expert (SME). Due to the manager's influence, the project team is concerned about the overall impact to the project.
What should the project manager have done?

الخيارات

  • A Consulted with the project sponsor on stakeholder roles and responsibilities
  • B Requested stakeholders to participate in project initiation and planning phases
  • C Obtained a list of the critical stakeholders from the project sponsor
  • D Identified and consulted stakeholders during requirements gathering