A project manager has been assigned to a new project. The project manager read the business case, charter, and statement of work (SOW) and scheduled a discussion with the sponsor about the scope, goals, and objectives. The project manager requested a meeting with the sponsor and the business analyst who performed the business case before setting up a kickoff meeting.
Why did the project manager request the meeting?

الخيارات

  • A To identify impediments, obstacles, and blockers for the team in the business case
  • B To identify and investigate perceived and potential misunderstandings in the business case
  • C To rewrite the business case to include additional objectives
  • D To verify the feasibility of the solutions in the business case